CONSTRUCTION PROGRAM

Works are planned to be undertaken in 4 key stages. The endorsed methodology took into account the feedback received, particularly from traders, during the consultation process.

The four (4) key stages of works are summarised below:

Stage 1 (starting May 2019)

Construction of the King William Road, Park Street and Mitchell Street intersection.

Stage 2 (starting June 2019)

Construction of the western kerbing.

Stage 3 (starting July 2019)

Central pavement replacement.

Stage 4 (starting August 2019)

Construction of shared spaces and footpaths.